The construction of the tram line from Krowodrza Górka to Górka Narodowa is in progress. The investment will take 2 years, and during this time the residents will have to take into account considerable nuisance and traffic difficulties. The latest photos & videos (check them out below) show how the construction is going.

Krowodza Gorka to Gorka Narodowa - Fast Tram line, Krakow, Poland
Krowodza Gorka to Gorka Narodowa – Fast Tram line, Krakow, Poland

Before the 5.5-kilometer-long track to the north of the city is built, a large area must be rebuilt on the section between the Krowodrza Górka terminus and the outskirts of the city on the national road No. 7. Officials from the Municipal Investments Board remind that the construction of the tram line to Górka Narodowa has begun July 8. The construction of the tram line from the Krowodrza Górka terminus to the Górka Narodowa is to take 2 years.

Cutting down trees and leveling the ground

The first stage of works can hardly be called spectacular, but it is a necessary stage to be able to start the main works: detours are being built, demolition works and preliminary archaeological surveys are underway, underground utilities are being repositioned. Recently, excavations of foundations for segments of the concrete structure, the so-called bathtub, the line of which will run between Kuźnica Kołłątajowska and Banacha Streets. This solution is to reduce the nuisance for the inhabitants of the surrounding buildings” – emphasize in ZIM.

Greenery is gone! Trees replanting?

As part of the construction of the Krakow Fast Tram to the Górka Narodowa, only the greenery that collides with the planned road and tram system has been cleared and reduced to the necessary minimum. To implement the project, 3,477 pieces of woody plants (deciduous and coniferous) will be removed in total.

Due to the extensive infrastructure of the project and collisions with many technical networks, tree plantings in the investment area cannot be carried out in a 1: 1 ratio. Nevertheless, within the boundaries of the investment, 2,680 tree plantings were planned, and the missing 797 trees will be planted as replacement plantings on plots belonging to the Municipality of Krakow.

November 2020 – The road work for the new tram line between Krowodza Gorka and Gorka Narodowa – Krakow, Poland

Where will the tracks lead?

  • From Krowodrza Górka (where the existing loop will be completely rebuilt), the tram will travel through the green area between the car showroom and the hospital.
  • At the intersection with ul. Opolska, a two-level intersection will be built. We will go down Opolska Street and the tram line will go higher.
  • Then the tram will go straight to ul. Pachoński. Before the crossing with Pachońskiego, Park & ​​Ride parking is planned.
  • The line will run along ul. Pachońskiego, then slightly turn right, connecting the intersections of Pachońskiego and Zielińska streets, and Białoprądnicka and Bularnia streets.
  • Between the intersections with ul. Bularnia and Pleszowska, the tram will turn left and reach Górnickiego Street, and further, on the southern side of ul. Pachońskiego, to Siewna Street.
  • At Siewna, the track will be moved to the northern side of the road and between the buildings (behind the buildings at 30 and 32 Siewna Streets) it will reach ul. Bociana.
  • The tram will reach building No. 17 along Bociana Street, where it will turn north and through the area of ​​the existing concrete plant, towards the railway tracks.
  • After passing under the railway tracks, the tram will cross ul. Kuźnicy Kołłątajowskiej and ul. Słomczyńskiego, and then behind the estate at ul. Banacha will go straight ahead for a while to turn right towards al. 29th of November. The loop is planned south of ul. Belwederczyk.
Krowodza Gorka to Gorka Narodowa - Fast Tram line, Krakow, Poland
Krowodza Gorka to Gorka Narodowa – Fast Tram line, Krakow, Poland

What does the investment include?

The route of the Krakow Fast Tram to Górka Narodowa also includes a two-chamber road tunnel with a length of approx. 100 m along ul. Opolska. This solution is to ensure a collision-free and problem-free passage of tram communication from northern housing estates to the city center.

The investment planned for implementation includes:
• construction of a tram line with a length of approx. 5 km along with full road infrastructure, including the construction and reconstruction of communication routes, the construction of bicycle paths, the construction of sidewalks and the construction of lighting
• reconstruction of the existing Krowodrza Górka tram terminus and construction a new tram and bus terminus in the area of ​​Górka Narodowa
• construction of 3 new traction substations and thorough modernization of 1 substation
• construction of a multi-level intersection with a tunnel along ul. Opolska
• construction of 3 parking lots in the Park & ​​Ride system:
– at the Krowodrza Górka tram and bus terminus with approximately 110
parking spaces
– at ul. Pachońskiego in the area of ​​ul. Szopkarzy with approx. 94 parking spaces
– at the Górka Narodowa tram and bus terminus – a two-level car park with
approx. 240 parking spaces
• construction of seven engineering structures:
– tunnel along ul. Opolska
– road flyover over the Sudół valley
– tramway overpass over the Sudół valley
– footbridge at the level of Szopkarzy and Danka Streets
– bridge over the Białucha river
– culvert on the Bibiczanka stream
– railway viaduct.

How much will it cost? Who will do it?

The task is carried out in the “design and build” mode. According to the contract signed on May 22, 2017, the contractor for the investment is a consortium of companies: Przedsiębiorstwo Usług Technicznych “INTERCOR” Sp. z o. o. and Przedsiębiorstwo Inżynieryjnych Robót Kolejowych “TOR-KRAK” Sp. z o. o. Before selecting the contractor, the City obtained decisions on environmental conditions (March 15, 2016).

The project is co-financed by the European Union from the Cohesion Fund under the Operational Program Infrastructure and Environment for 2014-2020.

The value of the project is in accordance with the financing agreement of 03/10/2017.
Total project value: PLN 378,914,203.93
Eligible expenditure under the project: PLN 216,735 206.67
Co-financing from EU funds: PLN 151,233,429.65

More info can be found, in Polish language, on the ZIM KRAKOW page (Zarzad Inwestycji Miejskich w Krakowie).