Krakow Project - Parking Lots

The Road Authority of the City of Krakow presented the immediate plans for the construction of city parking lots. The construction of park & ​​ride car parks in Bronowice and at the Hutnik hall in Nowa Huta is to begin this year. Tenders for the design of another 6 park & ride parking lots, including the extension of the existing facility in Ruczaj, are also to be announced. There are also plans for smaller neighborhood car parks.

This year, the Roads Authority of the City of Krakow plans to start the construction of 2 park & ​​ride parking lots. The first of them, for about 200 places, is to be built as part of the construction of the transfer junction in Bronowice.

Parking park and ride Bronowice

The contract for the construction of the node in Bronowice has been signed, we have concepts, now the contractor will start design works, then construction works – we plan that they will start at the end of the year

ZDMK

As part of the investment, a public transport bus station will be designed, equipped with the infrastructure necessary for passenger service, in particular: bus parking spaces, stops, ticket sales points, waiting rooms, information systems, and toilets.

The station will be located inside the connector of the road junction at ul. Balicka and the Home Army. The roofing bus station is to be the first tier multi-level parking for cars where the driver and leaving your vehicle will be able to change for the tram, bus, or train (park and ride systems). The investment is to be carried out by Budimex, which submitted a tender for PLN 51.6 million.

“Suche Stawy” park and ride parking at the Hutnika Kraków hall

In the case of the park & ​​ride car park “Suche Stawy” Suche Stawy, ZDMK plans to announce a tender so that the first works will start this year. The car park is to be built in the vicinity of the tram stop “Suche Stawy”, the Sports and Entertainment Hall “Suche Stawy”, the City Stadium Hutnik Kraków (Suche Stawy), the Sports and Recreation Center Com-Com Zone Nowa Huta.

This parking lot for approx. 90 vehicles has been planned for several years. The idea for this investment is to renovate the damaged surface of the existing above-ground car park in front of the Hutnik hall made of concrete slabs. The lighting will also be recreated with the electricity supply system.

In order to adapt the car park for the needs of the “park and ride” system, devices with the parking system software will be installed. Among them, there will be terminals, barriers, automatic cash register, monitoring, and a visual information system – boards informing about the car park filling status.

Krakow Project - Parking Lots
Krakow Project – Parking Lots

More park & ​​ride car parks in Krakow are planned

In addition, it is planned to announce a tender for the development of design documentation along with obtaining construction permits for the following tasks:

  • extension (superstructure) of the P&R Czerwone Maki car park in Ruczaj;
  • P&R “Mydlniki SKA” (SKA – fast agglomeration railway) car park, next to the railway stop (ul. Balicka-Gradowa);
  • P&R “Bieżanów-Drożdżownia SKA” car park at the Kraków Drożdżownia railway stop (area at the intersection of Rakuś – Zamłynie – Lipowskiego Streets);
  • P&R “Olszanica” car park at the railway stop, Powstania Styczeńowego street;
  • P&R “Księcia Józefa” car park (Wodociągowa Street);
  • parking in the vicinity of the Kraków – Opatkowice SKA railway stop.

Additional parking spaces for cars

As part of other investment tasks, ZDMK also plans the:

  • construction of a car park on the estate At Arka 5, on an area of ​​approximately 300 sq m (design documentation is to be developed in 2021);
  • construction of parking bays on the estate 2 Pułku Lotniczego in the area of ​​block 46 on the area of ​​approx. 260 square meters (design documentation is to be developed in 2021)
  • construction of parking spaces on the estate Green, bl. 15-16 (in 2021, the development of design documentation is to be completed and the construction of parking spaces on an area of ​​approx. 115 sq m is planned to start);
  • construction of parking spaces on the estate Spółdzielczy, bl. 8 (in 2021, the development of design documentation is to be completed and the construction of parking spaces on an area of ​​approximately 400 sq m is to be started);
  • reconstruction and extension of the car park in front of the Jordanian garden at ul. Kielecka 9 (in 2021, the development of design documentation is to be completed and the investment will be completed, parking spaces will be built on a total area of ​​approx. 290 sq m).

Housing estate car parks

As part of the parking space construction program, this year the following car parks are to be built:

  • on os. Metallurgical – a contract was signed for the development of design documentation (deadline June 2021),
  • at ul. Zuchów – a contract for the development of design documentation was signed (deadline June 2021).

The Rząska-Mydlniki-Wapiennik park and ride car park is being completed

The construction of the Rząska-Mydlniki-Wapiennik transfer junction with a park & ​​ride car park for 87 cars is near the end.
“The contractual completion date for the investment is April 2021. There are, among others, terminal equipment, technical building, installation of lighting poles, transformer station, target road marking” – informs the ZDMK.

Currently, works related to the construction of parking spaces at ul. Czerwieński.

Original article, in Polish language, can be found in Gazeta Krakowska.

Yours truly,

The Twisted Red LadyBug

Share: